SICSR-11308

[SICSR-11308] Incorrect Original Policy Period Validation on Claims Program linked to “Losses Occurring” Businesses  
Product Line: P&C
Component/s: Claims
Affects Version/s: SICS 4.7
Fix Version/s: SICS 20.1
Issue Links: is duplicated by SICSR-17307
Customer: DXC
External Issue ID: n/a

Problem:
System raises validation error CM0305 when creating a claim from the business, when the original policy period is not within insured period when attempting to link the claim to a claim program with period same as insured period, despite parameter do not validate OPP on Losses Occurring is activated

Solution:
the system should raise validation warning CM0382 instead of the above error

Workaround:
create the claim from the claim program

Root Cause:

Extent of Impact:

Impact on Existing Data

Recovery Method for Existing Data Affected